Supply Update & Colour Availability

Supply and Colour Range Update

As Christmas approaches, we would like to provide you with an update on our current supply timeframes.

Steel supply lead times

Our key suppliers COLORSTEEL® and ColorCote® continue to face significant supply challenges and are currently working to the following lead times:


COLORSTEEL® – currently have a minimum lead time of 16 weeks.

ColorCote® – has a minimum lead time of 7 weeks.


Please note, these lead times can vary, such that we are unable to guarantee an accurate delivery timeframe for any orders.


COLORSTEEL Colour Palette Changes

We have been advised by Colorsteel, that effective from 5th January 2022, they will be reducing the colours they supply. This palette will be in place until at least August 2022 and will now be as follows:


Flaxpod
Flaxpod Matte
Ebony
Ironsand
Greyfriars
Gull Grey
Sandstone Grey
Windsor Grey
Titania
New Denim Blue
Slate
Thunder Grey
Karaka



Please note the range of colours from ColorCote remain the same.

Also, as we get closer to the end of the year, some of our branches may start to run low on stock colours, so please contact your local branch for approximate delivery dates.


Changes in coatings to DD300, DD400 & Tray profiles


To advise also, that effective immediately the following products (steel based) will now only be available in these coatings:

DD300

0.55mm

MAXX

DD400

0.55mm

MagnaFlow/MAXX

Tray

0.55mm

MagnaFlow/MAXX



Please continue to check our website news section, for COVID-19 updates, and our supply updates section for our current lead times.


Also, with Christmas nearly upon us, please check our Holiday Closures to see the operating dates of your local branch and if you have any questions or queries, please don’t hesitate to contact us on 0800 DIMOND (346 663).



Finally, I would like to take the opportunity to thank you for your continued support, and to wish you a happy Christmas.



Nicholas Wheadon

Head of Sales | Dimond